Below: Early stages of pump house construction
After the concrete flooring in the pump house cured, the pump station components where delivered on an 18-wheeler. A large crane was then used to "drop in" the pad, control panel, and pumps as seen below.
Leibold was able tie in the pump house outtake line to the irrigation system last week during the warm weather. This is perhaps the most important leg of the pipeline, as it serves as the main artery to the entire irrigation system. As water exits the pump house, it goes through the schedule-40 steel "Z pipe" into the 14" mainline. This particular mainline requires a 6' deep x 60' long trench, as shown below.
Our plan is to use a combination of cultured stone and a darker, sand-colored stucco to finish the building exterior. Interior work remaining includes some electrical wiring, insulating, painting, and other details.
We will keep you updated as we finish things up, so visit the blog frequently.
No comments:
Post a Comment