We've had plenty of activity and challenge lately, with normal course maintenance, project work, and now this week, with excessive rainfall, but overall we are making good progress in all of these areas.
Course Maintenance:
Extended cool, cloudy, and wet conditions (at times) have significantly delayed seed germination in various rough areas where turf was very thin coming our of dormancy. Many of these areas were aerated, seeded, and covered with peat moss (to retain moisture and enhance germination) several weeks ago but are just now finally starting to germinate and establish. Rust disease as well as drought conditions last October likely contributed to the thinning we experienced and hopefully this recent overseeding as well as nutrient applications will soon provide good recovery.
Seed finally germinates. Notice the tufts of seedling. These are growing in the aerification holes.
The cooler temperatures, and windy and wet conditions through much of our so call "spring" have also caused delay in many typical tasks such as applying broadleaved weed control products, topdressing fairways (performed on about a third of our fairways), planting annual flowers, and some of our routine mowing programs. We're making steady progress in all these areas but we certainly have had more delays than in typical spring periods.
Project Work:
The Paddle Tennis Project began on May 13th with demolition of the old building and wooden decking and site preparation including removal of all the concrete piers which formerly held the old courts. The court contractor disassembled the courts but we assisted in moving 30 - 6'x30' court sections to a staging area where they will remain until a later time when portions will be returned to use.
Court section being transported to staging area
Pulling old concrete piers - a semi-truck load of them
Prior to excavation beginning, a couple poor quality trees were removed in the vicinity. This one was ready to fall without our help!
The hollowed out portion was filled with these huge wood borer larva. A delicacy in some countries!
After the court decks were removed excavation for the building basement took place (on Thursday and Friday, May 19-20) and on Friday my staff, using two of our dump trucks and two larger capacity rental trucks, hauled the excavated material to the site behind No. 5 Green. While the soil material was delivered (over 180 loads!) I began shaping it and blending into the existing berm. At 9 o'clock that evening we had completed hauling of approx. 750 yards of material and had it all shaped fairly close to finish grade. It was a long two days that day but we wanted to take advantage of relatively dry ground conditions and dry weather at the time, and without stopping at all except to fill fuel tanks, we tackled the task at hand. I am indeed grateful to my staff for this accomplishment. Had we been delayed just a couple days we would still be waiting to move this material as this week's rainfall would have prevented any movement of heavy equipment and any shaping.
We were all too focused on the task at hand to photograph the excavation, hauling, and shaping but this photo shows material in place and shaped. Hard to believe that this is the equivalent of about 75 semi-loads of soil.
Paddle House Basement - Where No. 5 berm soil originated.
Operator (that would be me) thought that he couldn't get this machine stuck. He was wrong!
Some gravel placed under the tracks and a helping pull from our 4X4 dump truck solved this little dilemma!
Excessive Rainfall:
We had several days of rain this week (hence the problem I had above - really, it was only a little water on the surface when I crawled over it - but I hit a pocket of soft mush and dropped about 2 feet!) and this resulted in nearly two days of lost course work and a delay in continuing progress on the No. 5 berm project and haul road repair.
A total of 3.5 inches of rain fell Weds. and Thurs. this week.
An all too familiar site last year... hopefully this doesn't have to be repeated again this year!
We will eventually get caught up, the course will dry out, we'll be able to finish the berm work, and then we'll move on to other tasks and projects. Lets hope we have some nice weather very soon!
Have a great Memorial Day!
No comments:
Post a Comment